Celbridge Sewer Network Improvement Project

Uisce Éireann Growth and Development Programme

Uisce Éireann, in partnership with Kildare County Council & South Dublin County Council, is improving the sewer network in Celbridge along the Dublin Road to support economic and social development of the area.

Uisce Éireann working in partnership with Kildare & South Dublin County Council is undertaking essential works to upgrade the wastewater network on the Dublin Road, Celbridge.These works will involve construction of almost 5km's of new gravity and rising main sewers.

This project is being delivered to support future development. It will also improve the capacity of the existing sewers, improving performance and reducing the risk of sewer flooding in the area. Coffey Construction Limited is working on behalf of Uisce Éireann to deliver this improvement project. 

Location
Kildare
Status
In progress
Type
Wastewater

What is involved as part of this project?

The project site is located east of Celbridge stretching for approximately 5km along the Dublin Road from Celbridge town and into South County Dublin. The first site can be characterised as opening at Primrose Hill Pumping Station on the Hazelhatch Road (R405) beside the local National School. From there it rounds the corner on to the Dublin Road and travels east towards Dublin connecting to an existing section of rising sewer constructed by South Dublin County Council (SDCC) as part of the ongoing Celbridge Link Road works. Primrose Hill Pumping Station will also be upgraded as part of this project.

The second site related to the rising sewer works from the Celbridge Link Road along Tubber Lane Road. This is a short section of rising sewer that terminates at Tobermaclugg Pumping Station and has been completed as of Q4 2022.

Figure 1 - Location of works

Works Update

All sewer pipelaying works have been completed. Following the required settlement period for temporary road surfacing, permanent road reinstatement works are planned to commence in February 2024.

In consultation with Kildare and South Dublin County Councils, reinstatement works will be carried out as follows:

Date Location Traffic Management
Tuesday 6th February to Monday 12th February R403 Adamstown Link Road to East of Orchard

Stop / Go system

Monday 12th February to Friday 16th February Shinkeen Road & Hazelhatch Road

Road Closure* at Hazelhatch Road, from the junction of R403 Dublin Road / Newtown Road to the junction of Shinkeen Road

Monday 19th March to Tuesday 5th April R403 Applegreen to East of Orchard

Stop / Go system

*Diversions in place:

Southbound vehicles on the R405/R403 (Liffey Bridge) towards Newcastle will be diverted left at the R403/R405/Ardclough Road intersection and will continue east along the R403 (circa 0.5km). They will then divert right and continue along the Shinkeen Road (circa 0.5km). They with divert left and merge onto the R405 again.

Northbound vehicles on the R405 from Newcastle toward Celbridge will be diverted right at the Shinkeen Road Junction. They will continue along the Shinkeen Road (circa 0.5km). They will then divert left onto the R403 and right across the Liffey Bridge.

Diversion routes will be clearly signposted. Emergency and local access will be maintained.

Contact details for further information

For further information on this project, please contact Uisce Éireann on 1800 278 278.